Rooftop solar and battery storage for the M62 and A1 logistics belt, factories and farms
Few parts of Yorkshire have as much big-shed roof space as the Wakefield district. Distribution parks sit where the M62 meets the M1 and A1(M), and new logistics schemes are going up on old colliery land. Most of these roofs still generate nothing. BrightEdge Solar designs and installs commercial solar panels and battery storage for warehouses, factories, offices and farms in Wakefield, Castleford, Normanton, Pontefract, Knottingley and the villages between. We’re based in Beverley, about 52 miles away. Our nearest commercial job is a manufacturer’s roof in Rotherham, about 23 miles south.
| Job | Distance from Wakefield | What we did |
|---|---|---|
| Pyronix, Rotherham | about 23 miles | 69.16 kWp SolarEdge system with optimisers on a new insulated trapezoidal roof |
| Care home, Clifton, York | about 35 miles | 47.08 kWp on a flat membrane roof, lightweight ballasted system under 32 kg/m² |
| Industrial estate, Chadderton, Oldham | about 41 miles | 99.44 kWp across 7 units with 7 separate G99 connections |
| Integra Buildings, Paull | east of Hull | 257 kWp industrial rooftop array, 220 kW of inverters |
| Industrial unit, Doncaster | South Yorkshire | 86 kWp: 187 DMEGC 460 W all-black panels on a profiled metal roof, SolarEdge SE66.6K with optimisers |
Yes. We cover the whole Wakefield district, including Castleford, Normanton, Pontefract, Knottingley, Ossett, Horbury and South Kirkby. Our nearest commercial job is in Rotherham, about 23 miles away.
Northern Powergrid, in its Yorkshire licence area. We submit the G99 application and deal with them for you.
Yes. On an estate in Oldham we fitted 99.44 kWp across seven units, each with its own inverter, metering and grid connection.
Yes, with your landlord’s consent. We provide the drawings and structural information landlords usually ask for, and a Power Purchase Agreement can suit tenants who don’t want to own the panels.
The G99 application typically adds 8–12 weeks before installation. Time on site depends on the system size, and we plan it around your operations.