Grid connection for commercial solar and battery storage

G99 Applications Explained: Connecting Commercial Solar and Batteries to the Grid

Before most commercial solar or battery systems can be switched on, the network operator must approve the connection. That approval is called G99, and BrightEdge Solar handles the G99 application for you.

See also: Commercial Battery Storage | Warehouse & Industrial Solar

See if we cover your area
Delivered For
Boeing Integra Indurent RAF NHS Modulek Biffa Fire Service Boeing Integra Indurent RAF NHS Modulek Biffa Fire Service

G99 in plain English

G99 applies to anything larger. The DNO must approve the system before it’s installed.

Almost every commercial system needs G99 approval

How the G99 application process works

From site check to commissioning

How the G99 process works

From site check to commissioning

Site and supply check

We look at your supply capacity, existing meters and any existing G99 approvals. Then we size the solar, inverter and any battery, and decide whether export limitation is needed.

Solar panels on a flat roof, shown on a laptop screen

Application and DNO assessment

We prepare and submit the G99 application with the technical details, equipment data and single-line diagrams. The DNO studies the impact on the local network and responds with a connection offer.

Solar panels on a roof, shown on a laptop screen

Offer and acceptance

The offer may approve your full export, approve it with an export limit, or require network work at a cost. We go through the options with you, then install once accepted.

Solar panels on a roof with a sunset sky, shown on a laptop screen

Commissioning

The system is tested and commissioned to G99 requirements, and the paperwork is sent to the DNO. For larger systems the DNO may want to witness the tests.

Commercial projects we've completed

See our case studies for commercial and agricultural projects we’ve completed.

86 kWp rooftop solar, Doncaster

The client wanted a SolarEdge system with a permanent roof safety line, using panels from the end client’s approved list. We installed 187 DMEGC 460 W all-black panels, covering about 370 m² of the profiled metal roof, on Clenergy trapezoidal rail laid out around the rooflights. The system runs on a SolarEdge SE66.6K Synergy inverter with S1200 optimisers (two panels per optimiser). We sized the inverter to fit the site’s existing G99 approval, which had been granted for an older 60 kW unit, and a SolarEdge ONE Commercial Controller handles G99/G100 export limitation. Emlite MID meters with 4G remote reading record generation. Temporary GRP covers protected the rooflights during the install, and we fitted a permanent 72 m Soter II Man-Safe lifeline for safe future access.

99 kWp rooftop solar on a warehouse, Oldham

99 kWp rooftop solar on a warehouse, Oldham.

Aerial view of industrial buildings with rooftop solar

FAQ

Frequently asked questions

If it can export more than 16A per phase, yes. Almost every commercial system does.

Typically 8–12 weeks, sometimes longer on constrained networks. We start the application early.

We do, as part of the project. We also deal with any DNO queries.

If the combined system can export above the G98 limit, yes, or the DNO may need to be notified of the change. We check this for you.

The DNO may limit your export or ask for network upgrades. Export limitation or a battery can often make the project work within the limit.

Northern Powergrid covers Hull, East Yorkshire and much of the North East.

What if the DNO limits my export?

A limited export offer doesn’t have to stop a project. G99 is published by the Energy Networks Association, and the options include:
  • Export limitation (G100). A controller monitors the site connection and throttles the inverter so the agreed export limit is never exceeded. You still use everything you generate on site.
  • Battery storage. Instead of wasting curtailed generation, a commercial battery stores it for use later in the day.
  • Sizing to an existing approval. Where a site already has G99 approval, we can sometimes size the new inverter to fit within it.

What BrightEdge handles for you

  • Checking your supply, metering and any existing approvals
  • Designing the system to give the best chance of a workable offer
  • Preparing and submitting the G99 application
  • Dealing with DNO queries and explaining the offer
  • Designing export limitation and storage where needed
  • Commissioning and sending the paperwork to the DNO
Any DNO costs are shown separately in your quote, so you can compare like for like.

Planning a commercial project?

See how G99 fits into a full project on our warehouse and industrial solar and commercial solar in Hull and East Yorkshire pages.

Talk to us about your grid connection

Send us a recent electricity bill and details of your supply, and we’ll tell you what’s likely to be involved in connecting solar or a battery at your site.

Call 01482 765063 · info@brightedgesolar.com

BrightEdge Solar Ltd, Colonial House, Swinemoor Lane, Beverley HU17 0LS. MCS certified (NIC-601602). RECC member.